Vertical Radiator
Integrated radiator on GPU base frame makes the unit installation faster and more easily. A remote radiator is also possible if you wanna save the noise and have limited space.
Integrated radiator on GPU base frame makes the unit installation faster and more easily. A remote radiator is also possible if you wanna save the noise and have limited space.
The battery system is arranged on the steel structure, on the side of the generator, which is maintenace-free.
The engine, alternator and radiator are installed on the same anti-corrosion base frame via anti-knock pad.
Island model, several units in parallel , single unit parallel with the grid or several units in parallel with Mains. You can achieve any one of them with this smart control system.
Maintain Item | Part number | Part model | Location | Quantity | Supplier |
Oil filter | 1000241448 | JLX-422C | Engine | 2 | Powerlink |
Lubricating oil | Engine | 42L | Powerlink | ||
Air/oil separator element | 1000235839 | Engine | 1 | Powerlink | |
Air filter element | 1000197158 | LJ45500 | Engine | 1 | Powerlink |
Spark plug | 1000301480 | IFR7AH4D | Engine | 6 | Powerlink |
Gas filter element | 1000292420 | Engine | 1 | Powerlink | |
Cylinder head assembly | Engine | 1 | Powerlink | ||
Cylinder head bolt | Engine | 6 | Powerlink | ||
Cylinder head bolt | Engine | 20 | Powerlink | ||
Cylinder head gasket | Engine | 1 | Powerlink | ||
Repair package | 1 | Powerlink | |||
Total of parts cost | |||||
Check the engine control system program,smoke exhaust, and valve clearance | 0.5 | Powerlink | |||
Check the ignition coils, change it if necessary | 0.5 | Powerlink | |||
Check the high voltage cable, change it if necessary | 0.5 | Powerlink | |||
Check engine intake air priessure, clean the intercooler if the data is abnormal | 0.5 | Powerlink | |||
Check and adjust the ignition order | 0.5 | Powerlink | |||
Change lubricating oil | 4.0 | Powerlink | |||
Change oil filter | 0.5 | Powerlink | |||
Change air/oil separator element,Gas filter element | 1.0 | Powerlink | |||
Change air filter element | 1.0 | Powerlink | |||
Change safety filter element | 1.0 | Powerlink | |||
Change spark plug | 2.0 | Powerlink | |||
Change cylinder head assembly | 8.0 | Powerlink | |||
Change cylinder head bolt | |||||
Change cylinder head gasket | |||||
Change repair package | |||||
Systematic recording | 2.0 | Powerlink |
Integrated radiator on GPU base frame makes the unit installation faster and more easily. A remote radiator is also possible if you wanna save the noise and have limited space.
The battery system is arranged on the steel structure, on the side of the generator, which is maintenace-free.
The engine, alternator and radiator are installed on the same anti-corrosion base frame via anti-knock pad.
Island model, several units in parallel , single unit parallel with the grid or several units in parallel with Mains. You can achieve any one of them with this smart control system.
A cogeneration system is both flexible and reliable, because of its efficient use of energy, industrial-scale cogeneration is more economical and environmentally attractive than conventional fossil fuel power plants.